Energy and Resources Minister Lily D’Ambrosio has revealed that Victoria has exceeded its 2025 renewable energy target, with renewables accounting for 44.6% of the state’s electricity generation last year—well above the legislated 40% benchmark.
The figure exceeds the 40 per cent target set under the Renewable Energy (Jobs and Investment) Act 2017 — a target the state actually passed on the way to a final 2025 annual tally.
The Department of Energy, Environment and Climate Action had already reported a renewable share of 39.1 per cent for calendar year 2024, meaning the final 2025 result of 44.6 per cent represents a strong accelerating trajectory from a base of just 5.7 per cent in 2006.
The milestone is the product of years of sustained investment. Wind and solar projects have proliferated across regional Victoria, rooftop solar has boomed on suburban rooftops, and successive government auction rounds have steadily contracted new generation capacity.
But the Victorian Auditor-General’s Office (VAGO), which tabled its audit Managing the Transition to Renewable Energy on 3 December 2025, offers a more sober assessment of what comes next.
What the Auditors Found
The VAGO report confirmed that Victoria is on track to meet its 2025 target under every plausible modelling scenario — a finding that validates the Minister’s announcement.
Using the same methodology as the Department, auditors independently reproduced its reported renewable share figures back to 2020, and extended their modelling forward across multiple demand and generation scenarios for 2025.
In all of them, Victoria clears 40 per cent, with projected shares ranging from 41.5 per cent to 44.9 per cent depending on assumptions around capacity growth.
But the audit’s central message is that 2025 was the easy part.
The next target — 65 per cent renewable energy by 2030 — is a far steeper climb. The Department itself advised government in 2024 that Victoria was tracking towards only a 58 per cent renewable share in 2030, following the closure of the Yallourn coal-fired power station in mid-2028.
Even with Victoria’s full allocation under the Australian Government’s Capacity Investment Scheme (CIS) — comprising at least 5 gigawatts or 11 terawatt hours of new renewable generation — the department estimated it would reach only 61 per cent.
Hitting 65 per cent will require additional Victorian Government support on top of the federal scheme.
Beyond 2030, the targets become even more demanding: 95 per cent renewable energy by 2035, coinciding with the planned closure of Loy Yang A, one of the state’s largest coal generators.
The Coal Dependency Nobody Is Talking About
For all the celebration around renewables reaching 44.6 per cent, the inverse of that figure is just as telling: coal still generated 59.2 per cent of Victoria’s electricity in 2023–24.
Brown coal, in particular, remains the invisible backbone of the state’s grid — providing around 70 per cent of overnight electricity supply when wind and solar generation are low and playing a critical role in stabilising the frequency and voltage of the network.
The government has signed agreements to close Yallourn by 30 June 2028 and Loy Yang A by 1 July 2035. Loy Yang B, whose owner Alinta Energy has flagged it may close earlier than its scheduled 2047 date if demand falls, has no formal closure agreement.
These closures are not distant abstractions. Yallourn’s exit is less than three years away. And the infrastructure meant to soften that blow is running late.
Critical Projects Are Behind Schedule
The VAGO audit identified delays across several of the key transmission and generation projects that the government’s plans depend upon.
The two transmission projects most critical to offsetting Yallourn’s closure — the Western Renewables Link and the VNI West interconnector — are both significantly delayed.
When the government signed the structured transition agreement with Yallourn’s operator EnergyAustralia in 2021, it assumed the Western Renewables Link would be completed by 2025 and VNI West by 2027–28.
Both projects are now not expected to be in service until 2029 and 2030 respectively — at least two years after Yallourn goes offline.
The consequences are serious. VNI West was designed to give Victoria access to Snowy 2.0’s long-duration hydro storage and to expand the state’s connection to the New South Wales electricity network.
Without it operating when Yallourn closes, Victoria will lack a key buffer during extended periods when wind and solar generation are low.
The offshore wind program is in even worse shape. The 2 gigawatt target that was legislated for 2032 will not be met. There is still no confirmed port to support the assembly and installation of offshore wind turbines.
The Victorian Government’s original plan to develop the Port of Hastings was rejected by the federal Environment Minister in January 2024 due to unacceptable impacts on nearby Ramsar-protected wetlands.
A revised proposal was resubmitted in June 2025 and remains under assessment. A multi-port strategy is being negotiated as a parallel option, but no agreements have been reached.
The government has already delayed its offshore wind auction process — originally scheduled for the third quarter of 2025 — until at least 2026.
Under the most optimistic scenario, Victoria could build 2 gigawatts of offshore wind capacity by end of 2033, a full year behind the legislated target. Further delays remain a real risk.
VAGO auditors also reviewed the second Victorian Renewable Energy Target auction (VRET2), which was designed to support six privately developed renewable energy projects operating by the end of 2024.
Only one — the Glenrowan Solar Farm — met that schedule. Two others have target operating dates in 2027. Three have no confirmed dates at all.
The Battery Bright Spot
Not every piece of news is grim. Battery storage is a genuine success story in the transition so far, and one of the few areas where Victoria is tracking ahead of schedule.
Under VAGO’s analysis, 1 gigawatt of battery storage capacity was already in service before July 2025, with up to 4.7 gigawatts in new capacity scheduled to come online by 2030.
If completed on time, this would put Victoria at up to 5.8 gigawatts of battery storage — more than double the legislated 2.6 gigawatt target for 2030.
The state-owned SEC Victoria is on track to deliver 700 megawatts of electricity storage across two projects before the end of 2027: the Melbourne Renewable Energy Hub (600 megawatts) and the SEC Renewable Energy Park at Horsham (100 megawatts).
A 350-megawatt, four-hour duration battery at Wooreen, committed by EnergyAustralia as part of the Yallourn closure agreement, is also under construction and expected online in December 2027 — just before Yallourn’s closure.
For short-duration peak demand events, this battery pipeline offers meaningful coverage.
AEMO data indicates there could be up to 4,505 megawatts of additional battery storage available in Victoria by winter 2028, which the auditors calculate would more than offset Yallourn’s closure for demand events lasting up to two hours.
The problem is what happens overnight.
The Overnight Problem
VAGO conducted a case study using real network data from 29–30 July 2024, when a high-pressure system sat over south-eastern Australia, bringing low wind speeds and limited solar output.
Victoria relied heavily on coal, gas, hydro and batteries to meet demand, and supply was tight — particularly during the evening peak.
The auditors then modelled what would happen if identical conditions recurred immediately after Yallourn closes in mid-2028.
The results expose a significant vulnerability.
After accounting for all committed and anticipated battery projects, gas generation, hydro and interstate imports, the modelling found an estimated overnight capacity gap of approximately 182 megawatts under the Australian Energy Market Operator’s demand forecast — rising to around 700 megawatts under a one-in-ten-year high-demand winter scenario.
Several compounding risks make this worse. Gas supply across Victoria is expected to fall 15.6 per cent by 2028 while demand for gas-powered electricity generation could double.
AEMO forecasts suggest that on high-demand days in 2028, gas demand could exceed supply by as much as 45.5 per cent — meaning gas-fired generators could be forced to run at only 6 per cent of required capacity on the worst days.
Victoria’s ageing gas plants, which will average 30 years old by 2028, also have a limited ceiling on sustained overnight output.
Hydro-electric generation is similarly constrained. Victoria’s largest hydro stations — Murray 1 and 2 — are limited by water-licensing rules under the Snowy Water Licence and the capacity of Geehi Reservoir. They cannot simply be ramped up on demand.
And crucially, other states face many of the same weather conditions simultaneously. When a high-pressure system parks over south-eastern Australia, it doesn’t just still the wind in Victoria — it reduces wind speeds across New South Wales, South Australia and Tasmania too.
On 29–30 July 2024, other states were also seeking to import electricity, not export it. AEMO has stated explicitly that extended still-weather events represent one of the most significant challenges to system security as coal exits.
Planning Has Lagged Behind Reality
The VAGO report is pointed in its criticism of how the Department of Energy, Environment and Climate Action has approached risk in its planning advice.
When the government negotiated the Yallourn closure agreement in 2021, the Department’s advice assumed both VNI West and the Western Renewables Link would be operational before Yallourn closed. It proposed no contingencies if they were delayed. Both are now delayed by at least two years.
When offshore wind targets were set in 2022, planning was based on a single scenario that assumed incremental delivery from 2029 and did not account for port risks.
The 2032 target will not be met, and the estimated cost of offshore wind has risen four to five-fold since that modelling was done.
The Department has also not provided VAGO with analysis of electricity supply risks during extended dark, still and cold weather conditions — despite AEMO explicitly flagging this as a major emerging challenge.
VAGO made four recommendations, all accepted by the relevant agencies.
These cover: facilitating sufficient transmission capacity to connect CIS projects; ongoing monitoring of electricity supply adequacy under different scenarios; applying better risk and uncertainty frameworks to transition planning; and taking concrete steps to address firm energy gaps as coal stations close.
The government’s overall reliability picture has improved. Under AEMO’s 2025 forecasts, electricity shortfalls against national reliability standards are not expected until 2030–31 under the base scenario — an improvement on the 2024 forecast, which pointed to shortfalls from 2028–29.
But the auditors note this improved picture rests on a series of assumptions about project timelines and demand that have, historically, proven optimistic.
The Road to 2035
Beyond the immediate challenge of replacing Yallourn, the trajectory to 95 per cent renewable energy by 2035 requires a pace of development that dwarfs anything Victoria has achieved before.
The Victorian Transmission Plan assumes 19.5 gigawatts of new generation and storage capacity will be built between 2025 and 2040 — requiring the commissioning of 1.3 gigawatts per year on average.
Victoria’s actual track record since 2010 is 0.5 gigawatts per year.
AEMO’s modelling in the plan assumes 4.1 gigawatts of new onshore wind and solar capacity will be commissioned by 2028–29 alone — a 70.7 per cent increase on current capacity, and double the total growth achieved from 2020–21 to 2024–25.
Electricity demand is also growing faster than planners anticipated. AEMO’s 2022 modelling forecast a 1.8 per cent fall in Victorian demand for 2024–25. Actual demand grew 3.5 per cent annually.
In June 2025, winter peak demand hit a record — running approximately 7 per cent above AEMO’s own high-demand forecast. Data centres alone are generating inquiries representing more than 10 gigawatts of new electricity demand in Victoria.
What the Milestone Actually Means
Victoria exceeding its 2025 renewable energy target is a legitimate achievement, and the Minister is right to mark it.
It represents two decades of incremental but compounding investment, policy reform, and technological change. The growth from 5.7 per cent renewable generation in 2006 to 44.6 per cent today is a genuine transformation of the state’s energy mix.
But the VAGO audit offers an important corrective to uncritical celebration. The 40 per cent target was always the beginning of the climb, not the summit.
The targets ahead — 65 per cent by 2030, 95 per cent by 2035 — are set against a backdrop of coal plant closures, ageing gas infrastructure, contested transmission corridors, a stalled offshore wind program, and electricity demand growing faster than anyone forecast.
As the auditors put it: Victoria is on track to meet its 2025 renewable energy target. Meeting future targets will be more difficult.
The question now is whether the planning, investment and contingency thinking catch up to the ambition of the targets before the coal stations that still power the state’s nights and winters are gone.